PROJECT DETAILS

Owner :

Wangaratta Solar Farm Pty Ltd
Capacity (DC) :

29.9MWp (22MW AC)
Technology :

Single Axis tracking solar PV (circa 65,000 solar panels)

Generation (PV Syst) :

54,000-55,000 MWh/ yr
Financial Close :

Q2 2020
Target Construction Start :

Q3 2020
Target Generation Start :

Q1/Q2 2021
Project Life :

25 years
 

Land

  • 7km north east of Wangaratta

  • 64ha of “Industry” zoned land requiring minor site preparation including minimal tree removal, small dam filing and site drainage

  • Close proximity to grid and roads

Grid

  • 66kV distribution system grid connection (AusNet)

  • Local 66kV line has capacity for greater than 22MWac export, creating potential opportunity for a Stage 2 expansion of Project

  • Dedicated on site substation 22/66 or 33/66kV to be constructed

Planning

  • DA (planning approvals) obtained

EPC

  • EOI completed in 2019, Preferred EPC contractor identified but not appointed. EOI level design and costings completed. Equity Partner can appoint under full wrap or construction only contract.

PPA

  • Energy Estate also mandated to secure PPA opportunities in parallel with equity sale. Several potential off take discussions are live. 

SITE AREA PLAN

Address

Contact

Follow

Level 16, 414 Latrobe Street, Melbourne, 3000

Level 12, 4255 Pitt Street, Sydney, 2000

  • instagram
  • linkedin

©2019 BY WANGARATTA SOLAR FARM. PROUDLY CREATED BY SUBGREEN DESIGN